Project Details
About the Package Treatment Project

This package treatment project, carried out in Bilecik for Osmaneli OSB, has a capacity of 1000 Persons / Day. It has been conducted within Osmaneli OSB. The project will be completed in 2025 as a turnkey solution. Additionally, the design, equipment procurement, installation, and commissioning processes have been managed by our company. This ensures a coordinated and error-free delivery to the customer from a single source.
Technical Specifications and Capacity
The fundamental technical parameters of the project are summarized in the table below. This information provides a quick overview of the project scope, engineering requirements, and delivery process.
Applied Package Treatment Technology
Package wastewater treatment system is a compact solution pre-manufactured in a factory environment. All process equipment is gathered in a single module. It is transported to the site and commissioned within 1-4 weeks. This allows for installation that is 5-10 times faster compared to traditional concrete construction facilities. It also provides compact space utilization. The modular expansion capability offers long-term advantages.
OSB Wastewater Management
The wastewater of the Organized Industrial Zone is a heterogeneous mixture from different sectors. Acceptance standards of member factories are fundamental to success. Additionally, the central facility should be designed with a multi-barrier structure. Automation and continuous monitoring are essential for a modern OSB facility.
Conclusion and Reference Value
At the end of the project, the effluent has been produced with a quality that meets the SKKY (Water Pollution Control Regulation) discharge standards. Furthermore, the facility is equipped with a modern automation infrastructure. This maximizes operational continuity and energy efficiency. For detailed technical information, you can refer to the Package treatment guide. Additionally, our articles such as industrial wastewater treatment methods and SKKY discharge limits 2026 guide address different aspects of the subject.
For similar capacity and sectoral needs, our Arsistek engineering team provides free preliminary study and technical recommendations. In addition, we offer consulting services for capacity increase or modernization of your existing facility. With over 20 years of experience, we provide reliable solutions to the industry, especially in the field of package treatment. For more information, you can contact us through our contact page.
Frequently Asked Questions
Project Scope and Workflow
During the project, the following steps were carried out by our company. Thus, the turnkey delivery process was completed smoothly.
-
1
Wastewater characterization analysis and sample examination
-
2
Process design and engineering calculations
-
3
Mechanical, electrical, and automation documentation
-
4
Equipment procurement and factory acceptance tests
-
5
Field assembly and hydraulic testssite assembly and hydraulic tests
-
6
Biological adaptation and commissioning
-
7
Operator training and technical documentation delivery
-
8
SKKY compliance tests and official reporting