The wastewater treatment plant project carried out in Turkmenistan for AO Smith Inc. is - capacity. The project was completed in 2025 as a turnkey solution. Additionally, the design, equipment supply, installation, and commissioning processes were conducted within our company. This ensured a coordinated and error-free delivery to the customer from a single source.
Technical Specifications and Capacity
The main technical parameters of the project are summarized in the table below. This information provides an overview of the project's scope, engineering requirements, and delivery process at a glance.
Applied Wastewater Treatment Plant Technology
The industrial wastewater treatment plant targets a sector-specific composition. A multi-barrier approach is utilized. This approach encompasses pre-treatment, primary, biological, and advanced treatment stages. As a result, the effluent meets the discharge limits.
Sectoral Wastewater Assessment
Accurate engineering design is the key to the project's success. Wastewater characterization and target discharge limits determine the design output. Additionally, SKKY compliance is a minimum requirement for every project.
Outcome and Reference Value
At the end of the project, the effluent was produced with a quality that meets the SKKY (Water Pollution Control Regulation) discharge standards. Furthermore, the plant is equipped with a modern automation infrastructure. This maximizes operational continuity and energy efficiency. For detailed technical information, the Industrial Wastewater Treatment Guide can be reviewed. Additionally, our articles such as industrial wastewater treatment methods and SKKY discharge limits 2026 guide address different aspects of the topic.
For similar capacity and sectoral needs, our Arsistek engineering team provides free preliminary assessment and technical recommendations. In addition, we offer consultancy services for capacity increase or modernization of your existing facility. With over 20 years of experience in the field of wastewater treatment plants, we provide reliable solutions to the industry. For more information, you can contact us through our contact page.
Frequently Asked Questions
Project Scope and Workflow
During the project, the following steps were carried out by our company. Thus, the turnkey delivery process was completed smoothly.
-
1
Wastewater characterization analysis and sample examination
-
2
Process design and engineering calculations
-
3
Mechanical, electrical, and automation documentation
-
4
Equipment procurement and factory acceptance tests
-
5
Field assembly and hydraulic testssite installation and hydraulic tests
-
6
Biological adaptation and commissioning
-
7
Operator training and technical documentation delivery
-
8
SKKY compliance tests and official reporting