Bingöl Organized Industrial Zone

Year
2025
Region
Bingöl
Country
Capacity
800 m³ / Day Capacity
Process
Industrial Wastewater Treatment Facility
Client
Bingöl Organized Industrial Zone

Project Details

About the Bingöl Wastewater Treatment Plant Project

Bingöl - Bingöl Organized Industrial Zone

This wastewater treatment plant project, carried out in Bingöl for the Bingöl Organized Industrial Zone, has a capacity of 800 m³ / Day. It has been conducted under the Ministry of Industry of the Republic of Turkey. The project will be completed in 2025 as a turnkey solution. Additionally, the design, equipment supply, installation, and commissioning processes have been carried out by our company. This ensures a coordinated and error-free delivery to the customer.

Technical Specifications and Capacity

The fundamental technical parameters of the project are summarized in the table below. This information provides an overview of the project's scope, engineering requirements, and delivery process at a glance.

Project Technical Information
Project Location Bingöl
Client / Institution Ministry of Industry of the Republic of Turkey
Capacity 800 m³ / Day Capacity
Process Type Industrial Wastewater Treatment Plant
Completion Year 2025
Discharge Standard SKKY (Water Pollution Control Regulation)

Applied Wastewater Treatment Plant Technology

The industrial wastewater treatment plant targets a sector-specific composition. A multi-barrier approach is utilized. This approach includes pre-treatment, primary, biological, and advanced treatment stages. As a result, the discharge water becomes compliant with discharge limits.

OSB Wastewater Management

The wastewater from the Organized Industrial Zone is a heterogeneous mixture from different sectors. Acceptance standards of member factories are key to success. Additionally, the central facility must be designed with a multi-barrier structure. Automation and continuous monitoring are essential for a modern OSB facility.

Outcome and Reference Value

At the end of the project, the discharge water is produced at a quality that meets the SKKY (Water Pollution Control Regulation) discharge standards. Furthermore, the facility is equipped with a modern automation infrastructure. This maximizes operational continuity and energy efficiency. For detailed technical information, the OSB wastewater treatment plant guide can be reviewed. Additionally, our articles such as industrial wastewater treatment methods and SKKY discharge limits 2026 guide address different aspects of the topic.

For similar capacity and sectoral needs, our Arsistek engineering team provides free preliminary assessment and technical advice. In addition, we offer consulting services for capacity increase or modernization of your existing facility. With over 20 years of experience in the wastewater treatment plant field, we provide reliable solutions to the industry. For more information, you can contact us through our contact page.

Frequently Asked Questions

5 Soru
Our projects are carried out in a 6-step process: 1) Feasibility and Exploration - Site inspection, wastewater analysis, and capacity determination. 2) Project Design - Process selection, mechanical and electrical projects. 3) Manufacturing - Equipment production in our own facilities. 4) Installation - On-site setup and mechanical/electrical assembly. 5) Commissioning - Testing and performance validation. 6) Operational Support - Training, remote monitoring, and periodic maintenance.
The delivery time varies according to the size of the project. For packaged treatment systems, a period of 2-8 weeks is anticipated, for medium-sized facilities 2-4 months, and for large-scale industrial projects 4-6 months. An expedited production schedule can be implemented for urgent needs.
All our systems are under a 2-year parts and labor warranty. Defective parts covered by the warranty will be replaced free of charge. Additionally, we ensure the lifelong efficient operation of your facility with the option of an annual maintenance contract after the warranty period. Remote SCADA monitoring provides the opportunity for immediate intervention.
You can fill out our contact form for a free exploration and quote, reach us by phone, or send an email. Our expert engineers will review your project and prepare a customized solution and price offer based on your needs. The exploration and feasibility study are free of charge.
We provide services to all provinces across Turkey. Abroad, we have projects in Iraq, Azerbaijan, Libya, Saudi Arabia, and Central Asian countries. We can offer turnkey projects globally.

Project Scope and Workflow

During the project, the following steps have been carried out by our company. Thus, the turnkey delivery process has been completed smoothly.

  1. 1
    Wastewater characterization analysis and sample examination
  2. 2
    Process design and engineering calculations
  3. 3
    Mechanical, electrical and automation documentation
  4. 4
    Equipment procurement and factory acceptance tests
  5. 5
    Field assembly and hydraulic tests
    site assembly and hydraulic tests
  6. 6
    Biological adaptation and commissioning
  7. 7
    Operator training and technical documentation delivery
  8. 8
    SKKY compliance tests and official reporting