Project Details
About the Package Treatment Project

This package treatment project carried out for Çelikmen İnşaat A.Ş in Ankara has a capacity of 1000 Persons / Day. The project was completed in 2025 as a turnkey solution. Additionally, the design, equipment procurement, installation, and commissioning processes were conducted within our company. This ensured a coordinated and error-free delivery to the client from a single source.
Technical Specifications and Capacity
The fundamental technical parameters of the project are summarized in the table below. This information provides an overview of the project's scope, engineering requirements, and delivery process at a glance.
Applied Package Treatment Technology
The package wastewater treatment system is a compact solution pre-manufactured in a factory environment. All process equipment is gathered in a single module. It is transported to the site and commissioned within 1-4 weeks. This allows for installation that is 5-10 times faster compared to traditional concrete construction facilities. Additionally, it provides compact space usage. The modular expansion capability offers long-term advantages.
Residential Project Wastewater Characteristics
TOKİ and mass housing projects generate domestic wastewater. Sizing according to the number of users is critical. Furthermore, the modular expansion capability provides significant advantages for social structure projects. Rapid installation is preferred for package solutions that align with the construction process.
Project Scope and Workflow
During the project, the following steps were carried out by our company. Thus, the turnkey delivery process was completed smoothly.
- Wastewater characterization analysis and sample examination
- Process design and engineering calculations
- Mechanical, electrical, and automation documentation
- Equipment procurement and factory acceptance tests
- On-site assembly and hydraulic tests
- Biological adaptation and commissioning
- Operator training and delivery of technical documentation
- SKKY compliance tests and official reporting
Result and Reference Value
At the end of the project, the effluent was produced at a quality that meets the SKKY (Water Pollution Control Regulation) discharge standards. Additionally, the facility is equipped with a modern automation infrastructure. This maximizes operational continuity and energy efficiency. For detailed technical information, you can refer to the What is Package Treatment guide. Our articles such as industrial wastewater treatment methods and SKKY discharge limits 2026 guide address different aspects of the subject.
For similar capacities and sectoral needs, our Arsistek engineering team provides free preliminary studies and technical suggestions. In addition, we offer consulting services for capacity increase or modernization of your existing facility. With over 20 years of experience, we provide reliable solutions to the industry, especially in the field of package treatment. For more information, you can contact us through our contact page.